Project description

The Hunter Expressway was originally proposed in 1988 but the construction started in 2010 after 22 years. It provides a much needed east west link in the Hunter Valley, connecting Newcastle and the lower Hunter and hence reducing travel time by almost half an hour. The Eastern Section from F3 to Kurri Kurri comprises three viaducts through the Sugarloaf Range. The viaducts have a total length of 787 m and are up to 47 m in height above the ground.

Delivered products

mageba supplied not only the spherical bearings, shear keys and modular expansion joints for the viaducts but also a structural health monitoring system. The installed RESTON-SPHERICAL bearings are all equipped with the mageba high-grade sliding material ROBO-SLIDE and have a load carrying capacity of 30‘000 kN. The RESTON-FORCE shear keys transmit a total horizontal force of 8500 kN.
The supplied TENSA-MODULAR expansion jonts have a total length of 142 m and allow for a total displacement of 680 mm. In 2013 a hydrostatic tube balance monitoring system has been in installed on all viaducts.

Download project information (PDF, 1372 kb)

Больше информации

Ключевые данные

Products:

60 RESTON-SPHERICAL bearings / 12 RESTON-FORCE shear keys / 12 TENSA-MODULAR expansion joints / ROBO-CONTROL structural health monitoring system

Installed:

2011/2013

City:

Hunter, NSW

Type:

Viaduct

Length:

40 km freeway

Hunter Expressway_Installation

The mageba TENSA-MODULAR expansion joint during installation on the first viaduct

Hunter Expressway_steep gullies

The Hunter Expressway viaducts over Sugarloaf Range with its steep gullies.